Wednesday, December 19, 2012

Production Meeting - Tuesday Dec 18

Attendance
Fawn
Jeff M.
Mia
Jeff C.
Jesse
Kathryn

Mintues/notes
now through Jan 6th - Finish up choreography
Jan 7-12 - Finish up blocking, work music and dance
Jan 13-19 - Act stumble throughs and polishing music and dance
Jan 17-19 - Act run throughs
Jan 20-26 - All show runs with notes after. Only stopping when absolutely needed
Jan 27-31 - Tech Week
Wed Jan 16 - orchestra and cast rehearsal, Cast off book by this time

We need to confirm with CCPA that we can move the upright piano on and off stage every night for two weeks

There will be NO invited dress rehearsal

as of now Thursday Feb 7, there will be a brush up

Tech schedule:
Sunday Jan 27 - load in and possibly begin cue to cues
Monday Jan 28 - Cue to cue
Tuesday Jan 29 - First dress rehearsal, start dressing at 5:30 in green room/dressing room area
Wednesday Jan 30 - Run show
Thursday Jan 31 - Run show
Friday Feb 1 - Opening night

Next Production Meeting: Tuesday Jan 8, 8:30